pass4side@hotmail.com
Exam Number/Code: 1z0-222
Exam Name: Oracle purchasing 11i fundamentals
Language(s): English
Price: $ 98.00
Questons and Answers : 138 Q&As
Updated: 2009-12-08
It is well known that Other Oracle Certification 1z0-222 - 1z0-222 exam test is the hot exam of Oracle certification. gopass4side offer you all the Q&A of the 1z0-222 real test . It is the examination of the perfect combination and it will help you pass 1z0-222 exam at the first time!
The Other Oracle Certification 1z0-222 Questions and Answers as well as our other Other Oracle Certification 1z0-222 exam training tools are not only priced to be easy on your budget - but each one is also backed with our guarantee. gopass4side guarantees that after using our Cisco certification training tools, you will be prepared to take and pass your Other Oracle Certification 1z0-222 exam.
Our on-site online training experts create all of the Oracle 1z0-222 exam products available through gopass4side. Our main goal is to get your certified with a firm understanding of the core material. Whereas other online distributors only concern themselves with helping you obtain the paper, we strive to educate the certification candidate and better prepare them for their IT career.
Why choose gopass4side 1z0-222 braindumps
Quality and Value for the 1z0-222 Exam
100% Guarantee to Pass Your 1z0-222 Exam
Downloadable, Interactive 1z0-222 Testing engines
Verified Answers Researched by Industry Experts
Drag and Drop questions as experienced in the Actual Exams
Practice Test Questions accompanied by exhibits
Our Practice Test Questions are backed by our 100% MONEY BACK GUARANTEE.
Exam : Oracle 1Z0-222
Title : Oracle(r) Purchasing 11i Fundamentals
1. Which two are prerequisites for internally sourced requisitions? (Choose two.)
A. must have a valid shipping network
B. must be MRP generated requisitions
C. must be configured in multiple Oracle applications
D. must apply to all items whether internal or external
Answer: AC
2. You need a quick way to set up auto-sourcing for a Contract Purchase Agreement.
You perform these steps in the order shown:
What is the result (all subject to buyer's approval rules and CPA limits)?
A. A new standard Purchase Order is generated.
B. A new standard Purchase Order is generated and approved.
C. Neither A nor B; only releases against blanket purchase agreements are auto-sourced.
D. A new standard Purchase Order is not generated because a concurrent process also needs to be run.
E. A new standard Purchase Order is not generated because of a setup configuration error shown in the steps above.
Answer: D
3. Which four are true about setting the receipt routing defaulting rules? (Choose four.)
A. Supplier set-up supersedes Receiving options.
B. You cannot allow users to override receipt routing.
C. Item set-up supersedes Supplier set-up routing rules.
D. Supplier set-up supersedes Item set-up routing rules.
E. You must set a rule in the receiving options setup form.
F. You can allow a user to override receipt routing by changing a profile option.
Answer: ACEF
4. On a standard purchase order, the distribution line for an expense item with no encumbrance, which is not autocreated from a requisition, the buyer must manually enter the _____.
A. PO Budget Account
B. PO Charge Account
C. PO Accrual Account
D. PO Variance Account
E. Destination Variance Account
Answer: B
5. You are a buyer in the procurement department of ABC Corp. You associated supplier XYZ in the Approved Supplier list for the LAPTOP POWERSOURCE category, but BXT laptop power Adapters (Item Number BXT-8765) belonging to LAPTOP POWERSOURCE category are available only from supplier MNO.
You created a new ASL entry for item BXT-8765, and associated it with MNO.
For item BXT-8765 in the item master, the Must Use Approved Vendor flag is set to Yes.
When creating a requisition for item BXT-8765, which Supplier would be defaulted?
A. XYZ
B. MNO
C. No Supplier would default.
Answer: B
6. A buyer wants to change the supplier's name on the basis of an update that was part of a quotation. Which four document types would be affected by the change? (Choose four.)
A. Return
B. Payment
C. Requisition
D. Sales Order
E. Purchase Order
Answer: ABCE
7. You are implementing a procurement solution for ABC Corp.
The client has the following business requirements:
Which two workflows need to be modified? (Choose two.)
A. Requisition Approval Workflow
B. Purchase Order Approval Workflow
C. Create Purchase Order or Releases Workflow
D. PO Send Notifications for Purchasing Documents Workflow
Answer: BD
8. When defining suppliers, you can set all of these attributes except _____.
A. Default Currency
B. Default Payment Terms
C. Default Payment Method
D. Default Invoice Match Option
E. Default Purchase Orders Type
Answer: E